Scott Building

You Are Viewing

Bridge Works (various)

Bridge Works

 

Project 1
Project: Reinstatement of Riverbank and repairs to Stone Bridge Abutments Burnside North Cupar.
Client: Fife Council
Date: Completed October 2009
Value: £40,000
Structural/Civil Engineering Consultant: Thomson & Partners

The project was part of flood defence works requiring the repair and reinstatement of the river bank of a tributary flowing into the River Eden along with stone repairs and reinstatement of the adjoining bridge which carried traffic across. Work was carried out in a residential area where we had to allow for continuous use of the bridge, provide uninterrupted access into private properties and maintain footpath access where possible along the side of the river. The river flowed down parallel to Burnside North Road on one side with residential and park land used by the public on the other.
Project 2
Project: Stewart Melville School – Bridge Works to main Entrance.
Client: Stewart Melville School
Date Completed: July 2009
Value: £80,000
Client Project Manager: Fox Projects UK

The project was for the repair and reinstatement of a pedestrian main access bridge into the school. The bridge was a grade ‘A’ listed structure and work was undertake while the college remained in use requiring the careful management of the safety of the users and public during the works.

 

Project 3

Project Mary Erskine School Bridge Reinstatement
Client: Mary Erskine School
Completed; July 2009
Value: £45,000
Client Project Manager: Fox Projects UK
The ‘A’ listed bridge carried a cycle track over the road access into the school. A milk lorry had hit the bridge damaging both abutments and deck.
Scott Building was required to remove existing stonework to abutments and arch and carefully lat aside. New stone was ordered to replace damaged.
The work required the erection of temporary access and support to allow us to carefully remove and reinstate. The temporary works being altered to suit the phasing of the work.

 

Project 4
Project: Maucheny Bridge Repairs
Client: Perth & Kinross Council
Date Completed: June 2014
Value: £30,000
Repairs to parapets and buttress with associated repairs on road bridge over river maintain bridge in use during works.